Smyrna Bypass Track

Project included the construction and all related site work to construct a 13,790′ bypass track, 1,938′ track shift, and 3,375′ track raise. Polivka International worked with EMH&T on the design-build of a retaining wall, culvert extension, and grade crossing on this project.

Lucas Siding Extension

Siding extensions of approximately 7,003′ included the construction of turnouts, roadbed, construction pads, access drives, new culverts, and removal of existing main line bridge and replacement with box culverts.